Texas Data Center Power Pause Splits
Texas Governor Greg Abbott's order to halt new data center grid connections has divided industry leaders, creating uncertainty for projects awaiting power

Texas Governor Greg Abbott has ordered a pause on all new data center connections to the state's power grid. The directive, issued earlier this month, requires state agencies to audit each project's planned power and water use, ownership, and other details before connections can proceed.
Data center developers are split on the move. Some call it a politically motivated mistake that threatens Texas's digital infrastructure boom. Others argue it is a necessary step to manage overwhelming demand and ensure reliable power goes to responsible projects first.
Industry Reaction at DICE: South
Speaking at Bisnow's DICE: South event in Arlington, industry leaders voiced contrasting views. Skybox Datacenters Chief Development Officer Haynes Strader strongly supported the governor's action. "The reality is we need a much firmer grasp on who's about to get interconnected," Strader said. He argued it would ensure power supports "the right narrative in Texas."
In opposition, Gigabit Fiber CEO Tom Spackman called the freeze a "horrible decision." He said it undermines the free-market ecosystem that attracted developers to Texas. Spackman argued the audits will create a "beauty contest" driven by politics instead of objective economic measures.
The Scale of the Power Problem
The governor's office states the Electric Reliability Council of Texas (ERCOT) is considering over 474 gigawatts of requested power capacity from large projects. It claims 90% of those requests are from data centers. This requested load is more than five times the record demand on the state grid and is equivalent to connecting over 415 million new homes. The administration warns this growth could jeopardize grid stability.
Delayed Clarity and Project Impacts
The pause created immediate uncertainty for developers awaiting a critical milestone. ERCOT had been preparing to announce which projects would be included in "Batch Zero," the first group studied under a new planning system designed to clear a backlog. That decision, expected on August 7, would have prioritized projects for grid connections. Abbott's order, announced just days prior, delayed it indefinitely.
Strader, despite supporting the pause, expressed frustration. "We were all... very much looking forward to [Aug. 7] and getting a notification of where you stood," he said. "That is causing a lot of consternation."
Gigabit Fiber's Spackman said his company requested power three years ago and still lacks a clear place in the queue. He had hoped August would bring clarity but found only prolonged uncertainty.
The Argument for Audits
Several panelists argued the audits will benefit the industry long-term. They claimed the process will weed out speculative projects or those from firms unlikely to deliver. CleanArc Data Centers COO Lindsey Bruner said the required disclosures could improve public trust in a sector facing political opposition from both parties.
Bruner noted that projects outside city limits often face little oversight, which has left communities feeling blindsided. A public approval process, she argued, could help the industry move forward "in a more positive light."
Strader conceded the pause will cost many projects their chance. "It's going to stink for lots of people," he said. But he concluded that with requests totaling four times the grid's capacity, "something has to be done."